PROFESSIONAL SUMMARY
Registered Civil Engineer, Construction Cost Engineer, and Associate Cost Consultant/Quantity Surveyor with experience in cost estimation, quantity surveying, and construction cost control for large-scale projects. Proven ability to manage project budgets, evaluate variation orders, and deliver cost savings. Skilled in softwares like CostX and DimensionX, and project cost analysis with strong coordination and reporting capabilities
CORE SKILLS
Technical Skills:
Quantity Take-Off (Architectural & Structural); Cost Estimation & Cost Planning; Cost Control and Monitoring and Cost Analysis; Variation Order Evaluation; Bill of Quantities (BOQ) Preparation and Tendering; Cost Variance Analysis (Close-Out); Software: CostX, BIM360, DimX, PDFX, MS Excel, Word, PowerPoint
Professional Skills:
Project & Time Management; Analytical Thinking; Communication & Negotiation; Active Listening; Detail-Oriented; Team Coordination
WORK EXPERIENCE
Arcadis Philippines, Inc. – Associate Cost Consultant/Quantity Surveyor
March 24, 2025 – Present
• Perform structural and architectural quantity take-offs for variation orders
• Conduct cost analysis and forecast impacts due to design changes
• Validate contractor claims and coordinate with project management teams
• Lead reconciliation of variation orders with contractors and subcontractors
• Support pre-tender evaluations and cost planning activities
• Prepare Bills of Quantities (BOQ) for fit-out works
DMCI Homes– Construction Cost Engineer / Quantity Surveyor
July 31, 2023 – March 13, 2025
• Performed detailed cost estimation using CostX for budget rehashed
• Managed project budget of PHP 3.858 billion, achieving 6% cost savings
• Prepared and monitored accomplishment reports and progress tracking
• Developed Cost to Complete and Manhours to Complete reports
• Conducted cost variance analysis and supported project close-out
• Processed interim payments, retention, and contractor billing
• Evaluated variation orders for civil, structural, and architectural works
• Prepared Project Overall Completion (POC) reports
• Processed PRF/PRFS (Request of Materials), petty cash, and request for payment